High Priority
- Big River Well Development Project
- Expected Outcome:
- Issuance of RFQP: FY09 Quarter 1
- Consultant Contract: FY09: Quarter 3
- USGS Report: Assessment of Wetlands Impact: FY10 Quarter 2
- DEM Permit Application: FY 10 Quarter 3
- Water Management (Allocation)
- Pilot Program: Hunt River Basin Water Management Program
- Expected Outcome: Program Scope of Work & Resources: FY09 Quarter 3
- Pilot Program: Chipuxet/Mink River Basin Water Management Program
- Expected Outcome: Program Scope of Work & Resources: FY10 Quarter 2
- Water Use Efficiency & Conservation Program
- Expected Outcome: Program Scope of Work & Resources: FY09 Quarter 3
- New Water Allocation / New Source Approval Regulations
Medium Priority
- Emergency Interconnections
- Expected Outcomes:
- Coordinate/Prioritize Projects with WRP&U/CEO Committee Determinations Regarding Supplemental Projects: FY09 Quarter 3
- Completed Projects. See Capitol Plan Schedule
- Water System Supply Management Plans (WSSMPs) & Water Use Reporting
- Expected Outcome:
- Complete Current Five-Year Cycle of Plan Submittals: FY10
- Continue Annual Water Usage Reporting Program
- Bristol County Water Authority Projects
- Expected Outcome:
- Issuance of RFQP: FY09 Quarter 1
- Consultant Contract: FY09: Quarter 3
- South County Well Sites Acquisitions
- Expected Outcome:
- Acquisition of Land well # 336: FY09 Quarter 2
Low Priority
- Supplemental Water Projects
- Expected Outcome:
- WRP&U/CEO Committee Defined Approach & New GOB Justification: FY09: Quarter 3
- New General Obligation Bond: FY2012
- New Regulations for WSSMP
- Water Data and Atlas
- BRMA Land Use Management Plan